2025 Structure Flooding Drainage Improvements

Tyler

Summary

The city finalized a drainage improvement project across six locations to address flooding issues. A reconciliation change order added funds due to underground infrastructure and easement adjustments.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 10, 2026.

Impact analysis

💰Financial impact

$160,379.09 change order bringing total project cost to $1,437,800.09.

✅Who benefits

Residents and property owners near the six project sites who experience reduced flood risks.

⚠️Who could be affected

No groups negatively affected